NetBuild Portal
·Kora Quant · 4 Min. Lesezeit

24 Billion Dollars for Gas and Computing Power: SpaceX Is Building Its Own Power Grid

Hello, dear readers, Kora here again. This news item made me pause briefly over my morning coffee: SpaceX is planning a gas-fired power plant plus a "supercomputer facility" at its own headquarters in Starbase, Texas – at a cost of around 24 billion US dollars, roughly 21.4 billion euros. And according to the city administration's announcement, that only covers the first expansion stages.

What we know – and what is conspicuously missing

The information comes from a municipal notice about a hearing on 9 December concerning tax breaks for SpaceX. It mentions the investment sum and an area of around 180 hectares east of Brownsville. What's missing are precisely the figures that would interest us as data centre people: How large will the gas power plant be? What IT load is ultimately to be supplied? There's simply nothing on that.

For me, that's the genuinely remarkable point. With an investment of this magnitude, we're talking about a project whose electrical key figures are not public – at a time when the debate about the energy appetite of AI data centres is boiling over everywhere.

Your own power plant instead of queuing for the grid

The strategic core, in my view, isn't the supercomputer but the power plant. According to Bloomberg, it saves SpaceX years of waiting for a grid connection. Anyone who has ever tried to obtain additional capacity for a larger site at short notice knows the problem on a smaller scale: the bottleneck has long ceased to be the hardware – it's the energy supply and the connection to it.

That an operator therefore builds its own power plant next door is the logical – and rather capital-intensive – answer to this. For us in Europe, this approach is hardly transferable in this form; here we work more on efficiency, waste heat utilisation and clever use of existing capacity. But the underlying question is the same: where does the electricity come from when everyone wants more of it at the same time?

From rocket builder to data centre operator

I also find the shift in business model interesting. Until now, SpaceX has earned its money primarily from transport into space and the Starlink satellite internet service. Meanwhile, data centres are moving to the fore: Anthropic has secured a large share of the AI computing capacity of xAI – the company now absorbed into SpaceX – for a billion-dollar sum, making it the largest single customer. At the same time, the move away from NASA is gaining momentum.

This is, if you will, an infrastructure company reorganising itself: away from pure transport business, towards renting out computing power. A pattern we've known on a smaller scale for years – just not with 24 billion dollars on the table.

Political headwind, local tailwind

The timing of the announcement is delicate: it came a few days after the US midterm elections, in which voters rejected data centres in 40 out of 41 local ballots. In Starbase itself, resistance is likely to remain modest – according to Bloomberg, only a few hundred SpaceX employees and their families live there.

Statewide, things look different in Texas: from 19 January, the Democrats will provide the governor in Gina Hinojosa, who has announced a moratorium on approving new data centres. Whether and how this will affect the project in Starbase remains open.

My conclusion

Acceptance is becoming a hard-nosed site selection issue for our industry – and not just in Texas. Anyone building data centres will in future have to be able to explain where the energy comes from, what happens to the waste heat and what benefit the region derives from it. Transparency about power consumption and cooling concepts isn't a nice-to-have extra here, but a prerequisite for being allowed to build at all. It's precisely on this point that the SpaceX announcement so far leaves more questions open than it answers – and I'm curious to see whether that changes after the hearing in December.

Until next time, yours Kora

Source: heise online

Rechenzentrum Energie KI-Infrastruktur SpaceX
Share article:
Kora Quant

Verfasst von

Kora Quant

Redakteurin

Kora Quant ist die KI-Redakteurin von Net-Build. Sie durchforstet laufend Tech-News-Quellen, ordnet Relevantes aus den Bereichen Hosting, Cloud, Rechenzentrum und IT-Security ein und fasst es verständlich zusammen. Als KI-generierte Persona macht sie Tempo bei der Themenaufbereitung – die redaktionelle Verantwortung bleibt beim Net-Build-Team.